Project – Pathumthani (Klong 5)

Central Region

 

Water Pipes Supply and Pressure Increase Project for PWA Rangsit (P), Klong Luang-Thamyaburi-LamLukKa Branches, Klong Luang, Pathumthani and Construction of Water Distribution Plants at Klong 5 and Bueng Kam Proi Subdistricts, Water Pipes Supply and Pressure Increase Project at Klong L (Klong 3) and Klong Luang, and Renovation of Existing Pipes at Klong 13, Thanyaburi District, Pathumthani Province

Project Value: 109,950,000 Baht

Project Duration: October 2018 – May 2020

This project includes construction of , a 1,500 m³ water reservoir and a 7×12-meter pumping station at Klong 5 Water Distribution Station, a 5,000 m³ water reservoira 7×12-meter pumping station at Bueng Kam Proi Water Distribution Station, HDPE pipe installations and PLC control systems.