Project – Pathumthani (Klong 13)

Central Region

 

Water Supply Capacity Increase and Modification Project – from Capacity of 2,000 to 3,500 Cubic Meters Per Hour and Water Pipes Supply/ Pressure Increase for Provincial Waterworks Authority, Klong 13 Water Treatment Plant

Project Value: 260,000,000 Baht

Project Duration: March 2015 – June 2016

This project requires an urgent extension of 7 km water pipelines that had to be completed within 3 months after the commencement date to help resolve water shortage in the area. The project also includes modification of the existing water treatment plan from 48,000 m³ per day to 84,000 m³ per day and construction of a 10,000-m³ water reservior.