';

Project Duration:  October 2020 – February 2022

Project – Khon Kaen (Part 2)

North East Region

 

Provincial Waterworks Authority’s Water Supply Expansion Project – Khonkaen-NamPong Branches, MuangKhonkaen-Oubonrat-NamPong districts, Khon Kaen Province (Part 2)

Project Value: 538,788,000 Baht

Project Duration: October 2020 – February 2022

Scope of work for the project includes construction of a 10,000 m³-water reservoir, a 500-m³ water tower, a 10.00×29.50-meter water pumping station, a 4.5×4.5-meter gas and chlorine distribution station at Baan Samran and Ubonrat Water Purification Plants, and up to 1,200 mm. HDPE and steel pipes installation.